Progress

Sl. No. Item Details Underprogress Completed Untackled
1 Upto SG Top 30.60 Km - 30.60 Km -
2 GSB/ CTSB 30.60 Km - 30.60 Km -
3 WMM 30.60 Km - 30.60 Km -
4 DBM 30.60 Km - 30.60 Km -
5 BC 30.60 Km - 30.60 Km -
6 Flyover NH-40 Connect 1.58 Km - 1.58 Km -
7 Service / Slip Roads Length 22.61 Km - 22.61 Km -
8 Minor Bridges 16.00 Nos - 16.00 Nos -
9 Vehicular Underpasses 4.00 Nos - 4.00 Nos -
10 Light Vehicular Underpasses 3.00 Nos - 3.00 Nos -
11 Small Vehicular Underpasses 1.00 No - 1.00 No -
12 Flyovers 1.00 No - 1.00 No -
13 Overpass 1.00 No - 1.00 No -
14 Box Culverts 46.00 Nos - 46.00 Nos -
15 Side Drain 63.32 Km - 63.32 Km -
19 Bus bays 14.00 Nos - 14.00 Nos -
20 Boundary wall 63.69 Km - 63.69 Km -
21 Thrie Beam Crash Barrier 54.88 Km - 54.88 Km -
^